Six hours of outage a day: sizing a server room that stays up
Energy
Agence Ecofin reported load shedding averaging up to six hours a day in the country's main cities, with Brazzaville and Pointe-Noire at the front. At the same time, Congo enjoys roughly two thousand hours of sunshine a year, while fewer than half the population has reliable access to electricity. In other words: the problem is daily, and the hybrid answer is no longer a conviction, it is a calculation.
Almost nobody runs that calculation seriously. A "solid" UPS is bought, a generator is added, and on the third outage of the day the room goes down anyway. Here is the method we apply on a site survey.
Step 1 — Measure the real load, not the rated load
The sum of the ratings printed on your server power supplies bears no relation to what they draw. A server with a 750 W supply often pulls 200 to 300 in normal use. Conversely, the total systematically forgets: room cooling — often the largest item — PoE-powered switches and access points, the storage array, emergency lighting and access control.
The survey runs over a week, with a clamp meter or the rack's own sensors, recording peaks. Peaks size the system, averages do not.
Step 2 — Decide what really has to stay up
Keeping everything up for six hours costs a fortune. Segment it:
- What must never stop: network core, domain controllers, production database, carrier link. Often less than 30% of the total load.
- What can stop cleanly: workstations, test servers, printing. A controlled shutdown beats an abrupt cut.
- Cooling, a case of its own: a room without cooling heats up fast, and servers shut themselves down. Plan either partial autonomy on cooling, or a shutdown procedure triggered on a temperature threshold.
Step 3 — Choose between batteries, generator and solar
The three do not play the same role, and the commonest mistake is making one carry another's job.
- The UPS covers the instant cut and the switchover time. On IT loads, aim for the autonomy needed to start the generator and shut down cleanly — not for the whole day.
- The generator covers long outages. Its weak point is not power, it is operations: fuel on hand, automatic start tested, servicing kept up. A generator that will not start in January because it has not run since September is a textbook case.
- Solar changes the picture on daytime outages, which are the most frequent, and cuts fuel consumption. On a site that consumes during the day, a photovoltaic installation with storage is reasoned as an investment with a measurable return, not as a green gesture.
The three mistakes that cost money
- Sizing on power and forgetting energy. A 10 kVA UPS says nothing about autonomy: the battery bank determines it, and it ages. A three-year-old battery does not deliver what the datasheet promised.
- Not monitoring energy. UPS status, load, remaining autonomy and room temperature must arrive in the same tool as everything else — for us, PRTG or ManageEngine. Otherwise you learn about the battery failure on the day you needed it.
- Forgetting cycles. Six outages a day means several hundred discharge cycles a year. Equipment must be chosen for that duty: it is exactly what separates an office UPS from a server-room UPS, and a starter battery from a deep-cycle one.
And supply
Correct sizing is worthless if the spare part arrives in three months. Sea freight from Asia to Pointe-Noire is counted in weeks, and a twenty-foot container commonly costs between two and four thousand dollars — which weighs on a project's schedule as much as on its budget. We factor that in upfront: equipment chosen for locally available parts, and a safety stock on critical consumables. Our installations rely on Schneider Electric and Vertiv for UPS, distribution and cooling.
What we do on a site survey
- A week-long load survey, peaks included.
- Autonomy calculated per segment, against the real condition of the battery bank.
- Costed scenarios: UPS alone, UPS plus generator, adding solar — with the payback period.
- Energy brought under monitoring, on the same footing as the servers.